Wednesday, November 26, 2008

Still Wiring.....












Ok.....not real exciting but maybe some of you will find these a little bit interesting. The first 3 pictures show the hot & cold water manifold. The red hot water tubing hooks into the red valves on the left & the blue cold water tubing hooks into the blue valves on the right. The 4th picture shows the wires hanging from the electrical panel....and Leryl assures me he knows what they're all for & where they all belong. The last picture shows the handy dandy spool holder Mike made. It has worked well for the boys. I think they're down to wiring the oven, microwave, kitchen pendants & 3 little accent cans in the great room. Looks like another big job will soon be completed!
Happy Thanksgiving everyone!!!

Thursday, November 20, 2008

Plumbing & Doors






OK....more pictures for Bill. The white pipe is central vacuum. I painted the Tyvek yesterday to see what Sveldt Sage looks like. Leryl & Mike hung the garage man door & the door to the BBQ area. Now.....if the big garage doors would get here we'd be tight!!! They're still working on the wiring. I think they'll both be glad when it's done.

Saturday, November 15, 2008

Cans, Cans & More Cans.....

Leryl & Mike have all the downstairs cans mounted & most of the upstairs. Not real exciting photo ops but I'm supposed to document it all. A couple shots of plumbing for you, Bill!!! :)




































Friday, November 14, 2008

Drillin' & Pullin'.....



OK...Bill wanted pictures of the wiring. Nice box, huh? Tim, Maryal & Mom are here for the weekend. I put Maryal to work on sweeping & Tim is helping Leryl figure out the panel. The safe is installed & the framing around the tub is done. Plumbers are here today so it's busy out there.










Monday, November 10, 2008

One Door In.....


Double doors are in the great room! Gave the boys a bit of trouble as the concrete slab is not completely flat. They hung in there & got it done!!! I didn't do so well on the pictures but you get the idea. The blog will definitely slow down as drilling holes & pulling wires in not real exciting stuff to document! Thanks for checking & I'll do my best to keep it interesting. Penne......I didn't have a choice on the hardware. It's a special locking system built into this door.....my choice was in finish only. Oh well.......................

Wednesday, November 5, 2008

Got 'Em In!!!


OK.....the upstairs windows are in so I can quit nagging! Mike returned Monday evening, the windows went in yesterday and today they're off getting "stuff". They have to put in the central vac system and then I think they're on to electrical.....more shavings for me to sweep. Spud Hill & Moscow Mountain had a dusting of snow this morning.....it's coming!